Two troubleshooters handle service calls for 10 machines


Two troubleshooters handle service calls for 10 machines. The average time between service requirements is 18 days, and service time averages 2 days. Assume exponential distributions. While running, each machine can produce 1500 pieces per day. Determine:

(A) The percentage of time troubleshooters are idle

(B) Each machine’s net productivity

(C) If troubleshooters represent a cost of $150 per day, and machine downtime cost is $600 per day, would another troubleshooter be justified? Explain.

Request for Solution File

Ask an Expert for Answer!!
Other Subject: Two troubleshooters handle service calls for 10 machines
Reference No:- TGS0660543

Expected delivery within 24 Hours