To control your project you decide to use milestone


1. To control your project, you decide to use milestone analysis. Which of the below is not a benefit of using milestone analysis to control a project?

a. Milestones help align schedules with vendors.

b. Milestones can be used as signals to team members.

c. Milestones can motivate the project team.

d. Milestones ensure the WBS is followed.

2. You are the project manager of a large, virtual financial project. You want to improve the functioning of the project team. Which of the techniques below would not likely improve the effectiveness and efficiency of the project team?

a. Establish a code of conduct for the project team.

b. Create a process to handle conflict. Week 6 Lecture High performance work teams

c. Ensure all members of the team fully understand the project scope.

d. Hold face-to-face meetings whenever possible.

3. Stand-up meetings in agile project management do all of the following except which?

a. Provide project status. Week 6 Lecture Agile Project Leader

b. Report on anticipated issues.

c. Permit group problem resolution.

d. Enhance collaboration.

4. What document provides information on who is in charge of the IT support for a project and who reports to the IT person in charge?

a. The WBS

b. The RAM

c. The RACI

d. The OBS