What is the scope of the project what does it deliver


Read the following case to answer the following questions.

1. What is the scope of the project? What does it deliver?

2. Describe how the project tasks and work are organized.

3. What are the weak points with using bar charts for planning this project? What could cause this project to fail?

4. What could cause this project to fail, its risks?

A Bar Chart Case Example: An Aircraft Component Project

L-F (Lock-Flouris) controls Inc. is a company that designs and manufactures small electronic components, particularly for the aviation, defense, and space industries. It has received an order from an aircraft manufacturer to design and supply electronic control units that will be mounted in or near the engine bays of a new range of aircraft to be built in both civil and military versions. This small unit will contain a small number of electronic components, assembled on a printed circuit board, which in turn will be supported on an aluminium chassis. This assembly is to be encapsulated in epoxy resin to protect the components from the harsh environmental conditions of the engine bay. A cable connector and a pressure switch will also be mounted on the chassis, to protrude outside the encapsulated block. The small project described here is for the design and environmental testing of a small prototype batch. Our project ends with the issue of drawings for manufacture.

Figure 7.1 lists the main tasks for this project. The estimated duration, stated in days, has been entered against each task. in each case this is the best estimate of how long each task will take (the elapsed time), and it does not indicate the resources or work-hours required. The extreme right-hand column lists, for each task, the immediately preceding tasks that must be completed before the new task can start.

Figure 7.2 is the resulting bar chart. The planner has tried to observe the dependencies (logical constraints) given in the final column of the task list. For example, no environmental testing can take place before the ten prototype units have been made and functionally tested. However, the usual form of bar chart, shown here, does not allow these logical constraints or links to be shown. These can be dealt with mentally on this simple project, presenting no problem to a competent planning engineer. But, with any project of greater size there would be a considerable risk of producing a bar chart containing some logical impossibility. Also, there is a risk of introducing logical planning errors whenever the chart has to be rescheduled.

Vertical link lines can be added to bar charts to indicate dependencies (logical constraints) between two or more jobs. Figure 7.3 is a linked version of the bar chart of figure 7.2. This shows clearly, for example, that the determination of environmental parameters and main design cannot start before the customer has specified the project requirements. But some links, even for this tiny project, cannot clearly be shown on this kind of chart. This applies, for example, to tasks which are dependent on determining the environmental parameters. Most project management computer programs are capable of plotting linked bar charts, but the results are usually cluttered and difficult to interpret except for very tiny projects.

This project will be revisited later in this chapter to see how much more effective it would be for the L-F controls company to plan its work with critical path networks.

Bar Charts As Progress Monitoring Aids

Because bar charts are drawn to scale, they can be used to indicate progress. For this purpose a date cursor must be added, which is a vertical line placed on the chart at the review date (which is sometimes called time-now). If the chart is drawn or printed on paper, the date cursor can be formed by placing a straight edge or ruler vertically on the chart at the time-now date. Adjustable charts set up as wall charts often use a scarlet elastic cord or ribbon for the cursor line. Progress assessment is simply a matter of checking that all tasks (or portions of tasks) lying to the left of the date cursor have been completed. Late jobs are highlighted clearly by this method.

Bar Chart Limitations

The inability of bar charts to depict clearly the dependencies between different tasks has been demonstrated but bar charts have other limitations. Although it is possible to schedule more than 100 jobs using a proprietary adjustable wall chart, rescheduling is a different story. Setting up a complex plan in the first place might take a few working days but adjusting it subsequently to keep in step with changes might prove impossible. However, a project management computer system will solve this inflexibility problem.

For those who prefer to see their project plans always presented as bar charts, all competent project management software can convert plans using critical path networks into their equivalent bar charts, either with or without the links shown.

The visual effectiveness of a chart is lost when too many color codes are introduced, or when there are so many tasks shown in one view that it is difficult to trace their positions along the rows and columns.

Critical Path Networks

The idea for critical path networks germinated in several places before the Second World War, but it was in the US during the 1950s that they were fully exploited. They became more popular in the 1960s when suitable computer systems became available with which to remove the drudgery of scheduling and (particularly) rescheduling.

Network diagrams show all the logical interdependencies between different jobs. The planner can ensure, for example, that a set of tires is not scheduled for fitting before the wheels manufacture has been completed and the tires have been purchased. Such logical inconsistencies are easily possible with complex bar charts, where it is impossible to depict or see every logical constraint.

Another great strength of networks is that they allow priorities to be quantified, based on an analysis of all the task duration estimates. Those tasks that cannot be delayed without endangering project completion on time are identified as critical tasks, and all other tasks can be ranked according to their degree of criticality.

Networks cannot be used by themselves for resource scheduling. in this respect bar charts are superior and easier to understand, provided that the number of activities is very small. However, one important value of networks is that they assign time-based priorities to tasks and highlight critical jobs. That is a vital contribution to the resource scheduling process, and critical path network analysis is an essential precursor to resource scheduling. Resource scheduling is described in Chapter 8. Most project management software can schedule resources.

Even if no duration estimates are made and there is no time analysis, the benefits derived from drawing a network can be worthwhile. Networking encourages logical thinking. A planning meeting can be regarded as a productive form of brainstorming. it greatly helps to develop the project process. Not only does the network notation allow expression of all inter-activity dependencies and relationships, but there is also the important possibility that activities may be brought to light which might otherwise have been forgotten, and thus excluded from schedules, estimates, cost budgets, and pricing.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the scope of the project what does it deliver
Reference No:- TGS01065157

Expected delivery within 24 Hours