The following table has data regarding several activities associated with the implementation of a new delivery process for a new retail chain. The contract with the new retail chain states that starting on the 13th day from now, your firm will experience a penalty of $110 per day until the job is completed. Indirect project costs amount to $227 per day. The data on direct costs and activity precedent relationships are given in the table.

Delivery Process Project Data

Activity

Normal Time (Days)

Normal Cost Per Day

Crash Time (Days)

Crash Cost Per Day

Immediate Predecessor(s)

A

4

$1,004

3

$1,232

None

B

7

$1,411

4

$2,032

None

C

5

$2,020

4

$2,707

None

D

6

$1,263

5

$1,472

A

E

3

$915

2

$1,166

B

F

11

$2,517

6

$3,757

C

G

4

$812

3

$1,431

D, E

H

3

$394

1

$500

F, G

To complete this assignment, answer the following questions. Begin by drawing the project network diagram. A start node and end node are suggested (no more than 3-5 pages).

1. What are the options? What is the cost of each option?

2. What are the advantages and disadvantages of each option?

3. What completion date would you recommend? Why?

4. What is the total cost of your recommendation?

Requirements -

Draw the project network diagram. A start node and end node are suggested. Use direct quotations sparingly and judiciously

On the Word document, answer the prompts listed above in no more than five pages.

Request for Solution File

Ask an Expert for Answer!!
Project Management: To complete this assignment answer the following questions
Reference No:- TGS02431880

Expected delivery within 24 Hours