Problem Sets in Planning and Scheduling
Fence schedule. This deliverable requires that you assign durations for each activity and must have (1) a network diagram with clear labeling; (2) calculations for ES, EF, LS, LF, and total float; and (3) a red line that clearly marks/identifies the critical path.
Planter schedule. This deliverable requires that you assign durations for each activity and must have (1) a network diagram with clear labeling; (2) calculations for ES, EF, LS, LF, and total float; and (3) a red line that clearly marks/identifies the critical path.
Update: Durations have been added
| FENCE PROJECT |
| Activity |
Activity Description |
Predecessor |
Duration |
| A |
Mobilize |
|
2 |
| B |
Clearing and grubbing |
A |
2 |
| C |
Layout fence |
B |
2 |
| D |
Deliver posts |
C |
1 |
| E |
Auger post holes |
C, D |
3 |
| F |
Set posts in holes |
D, E |
3 |
| G |
Backfill and plumb posts |
F |
2 |
| H |
Deliver boards for fence |
G |
1 |
| I |
Install boards for fence |
H |
3 |
| J |
Paint fence |
H |
2 |
| K |
Plant shrubs along fence |
I, J |
3 |
| L |
Final inspection |
K |
1 |
| M |
Demobilize |
L 2 |
| PLANTER PROJECT |
| Activity |
Activity Description |
Predecessor |
Duration |
| A |
Mobilize |
|
2 |
| B |
Install security fence |
A |
2 |
| C |
Excavate planter foundation |
A,B |
4 |
| D |
Set forms |
B,C |
3 |
| E |
Set rebar |
D |
3 |
| F |
Order concrete |
E |
1 |
| G |
Place concrete |
F |
1 |
| H |
Strip forms |
G |
3 |
| I |
Deliver bricks to site |
G,H |
1 |
| J |
Construct masonry planter |
I |
4 |
| K |
Place soil in planter |
J |
2 |
| L |
Remove security fence |
K |
2 |
| M |
Demobilize |
L |
2 |