Theoretically, the system a ticket taker at Boone Pickens Stadium could process 335 entries per hour. A study has revealed that in realistic conditions an excellent and attentive ticket taker can actually only process 280 entries per hour. Jim Bob at gate three averages 203 entries per hour. Jim Bob's efficiency? Express as a percentage rounded to the nearest one decimal place (79.372% would be expressed as "79.4")