The projects are equally risky with a cost of capital of 10


Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000, annual cash flows of $30,000 for 5 years. The smaller project has an initial cost of $50,000, annual cash flows of $16,000 for 5 years. The projects are equally risky with a cost of capital of 10%. If the projects are independent, and you have been advised to prioritize the IRR method, which project or projects would you pick? IRR (Calculation/Excel/Formula)