The overall average on a process you are attempting to


the overall average on a process you are attempting to monitor is 50 units. the process standard deviation is 1.72. Determine the upper and lower control limits for a mean chart, if you choose to use a sample size of 5.

A) set z=3
B) set z=2.

 