A draw the project network using aon b identify the


Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows: Activity Time (in hours) Immediate Predecessors A 6.0 B 7.2 C 5.0 A D 6.0 B, C E 4.5 B, C F 7.7 D G 4.0 E, F a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length?