The mean time required to complete a certain type of


MUST SHOW ALL EQUATIONS USING EXCELL FORMATTING

Scenario Data: The mean time required to complete a certain type of construction project is 61 weeks with a standard deviation of 4.15 weeks.

Answer questions 1 - 4 using the preceding information and modeling this situation as a normal distribution.

Question 1. What is the probability of the completing the project in no more than 58 weeks?

Question 2. What is the probability of the completing the project in more than 62 weeks?

Question 3. What is the probability of completing the project between 58 weeks and 65 weeks?

Question 4. What is the probability of completing the project within plus or minus one standard deviation of the mean?