The lead time for production of a is two weeks develop the


The BOM for product A is shown next and data from the inventory records are shown in the table. In the master production schedule for product A, the MPS quantity row (showing completion dates) calls for 250 units in week 8. The lead time for production of A is two weeks. Develop the materials requirements plan for the next eight weeks for Items B, C, and D.

Data Category B C D
lot sizing rule p=2 FOQ=1000 LFL
lead time 2 weeks 1 week 2 weeks
scheduled recepts 100 (week 1) 0 0
Beginning On hand inventory 0 100 0

 