On-hand inventory levels for each item as shown in the


Given the bill of material for the printer cartridge (A) shown below, a gross requirement to build 170 units of A, on-hand inventory levels for each item as shown in the table below and assuming zero lead times for all items A, B, C, D, and E, compute the net requirement for each time.

Item On-Hand Inventory
A 50
B 50
C 90
D 70
E 15

 