The job was completed on december 15 2009 under the


Question - During 2008, Eaton Corp. started a construction job with a total contract price of $3,500,000. The job was completed on December 15, 2009. Additional data are as follows:

2009 2008

Actual costs incurred $1,350,000 $1,525,000

Estimated remaining costs 1,350,000 -

Billed to customer 1,200,000 2,300,000

Received from customer 1,000,000 12,400,000

Under the completed-contract method, what amount should Eaton recognize as gross profit for 2009?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: The job was completed on december 15 2009 under the
Reference No:- TGS02827637

Now Priced at $25 (50% Discount)

Recommended (95%)

Rated (4.7/5)