the following table shows the activity details of


The following table shows the activity details of a project. What the earliest the project can be completed?

Activity Days Predecessor ctivities

A 4 -
B 5 -
C 3 A
D 5 A
E 7 B
F 2 D,E
G 6 C,F

 