The following jobs are waiting to be processed at the same


The following jobs are waiting to be processed at the same machine center. Jobs are logged as they? arrive:

Due Date Duration? (days)

A 313 8

B 312 16

C 325 40

D 314 5

E 315 3

All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each job starts at the beginning of the day and finishes at the end of the day? (a job that begins on day 275 and takes 8 days will finish on day? 282, and the next job begins in the morning of day? 283). Compute all times based on initiating work on day 275.