The following activities are part of a new project that the


Problem:

The following activities are part of a new project that the firm is planning. If the project is planned using the critical path method, how would the network look? What is the critical path? Also, estimate the completion time for this project.

Activity

Immediate Predecessors

Times in Weeks

A

None

1

B

A

1

C

A

1

D

B, C

2

E

B, D

3

F

D, E

3

G

E, F

1