The firms tax rate is 35 and the required rate of return is


The most likely outcomes for a particular project are estimated as follows:

Unit Price: $50                                  Variable Cost: $30

Fixed Cost: $300,000                       Expected Sales: 30,000 units/year

However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10 lower than the original estimate. The project will last for 10 years and requires an initial investment of $1 million, which will be depreciated straight-line over the project life to a final value of zero. The firm's tax rate is 35%, and the required rate of return is 12%.

a) What is the project's NPV in the most likely scenario?

Solution Preview :

Prepared by a verified Expert
Basic Computer Science: The firms tax rate is 35 and the required rate of return is
Reference No:- TGS02836966

Now Priced at $10 (50% Discount)

Recommended (94%)

Rated (4.6/5)