The design capacity needed to achieve the required actual


In a job shop, effective capacity is only 43 percent of design capacity, and actual output is 68 percent of effective output. What design capacity would be needed to achieve an actual output of 11 jobs per week? What is its effective capacity?

a. The Design Capacity needed to achieve the required actual job outputs = (round to whole number)

b. The Effective Capacity needed to achieve the required actual job outputs = (round to whole number)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The design capacity needed to achieve the required actual
Reference No:- TGS02914382

Expected delivery within 24 Hours