Task predecessor duration days use ms project to develop


A project is made up of several tasks, as shown in the table below.

Task Predecessor Duration (days)

A - 7

B - 5

C A 6

D A 8

E B 9

F C 5

G D, E 4

The project is scheduled to begin on Monday, Dec 11, 2017.

Use MS Project to develop the project schedule. Obtain printouts of the Gantt Chart and the Network Diagram

Please using Microsoft to help me solve this problem