Suppose that you have 5 weeks instead of 8to complete the


Question: Below durations, what activities each must precede and the crash cost to reduce duration per? week:

Activity Duration Precedes Crash cost
A 2 B,C 300
B 2 E 100
C 4 F 175
E 1 F 140
F 2
400

Suppose that you have 5 weeks? (instead of 8)to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration.