Suppose a lean work center is being operated with a


Suppose a lean work center is being operated with a container size of 25 units and a demand rate of 100 units per hour. Also assume it takes 180 minutes for a container to circulate.

a. How many containers are required to operate this system?

b. What is the maximum inventory that can accumulate?

c. How many Kanban cards are needed?