Suad alwan the purchasing agent for dubai airlines has


Suad Alwan, the purchasing agent for Dubai Airlines, has found that the third plane it needed from a Brazilian manufacturer took that firm 20,000 hours to produce. Using an 75% learning curve and a $40 per hour labor charge, Suad wishes to calculate what thirteen additional planes should cost

Time required for the 11th unit =

Cost of the 11th unit =

Time required for the 12th unit=

Cost of the 12th unit =

Time required for teh 13th unit

Cost of the 13th unit =

Time required for teh 14th unit=

Cost of the 14th unit =

The combinded time for the four planes = hours

The combinded cost for the four planes = dollars