As the estimator for Rajendra Tibrewala Enterprises, your job is to prepare an estimate for a potential customer service contract. The contract is for the service to diesel locomotice cyclinder heads. The shop has done some of these in the past on a sporadic basis. THe time required to service the first cyclinder head in each job has been extactly 3 hours, and similar work has been accomplished at an 70% learning curve. The customer wants you to quote the total time for a batch of 12 and 20

A) The total amount of hours to build the 12 units =

The total amount of hours to build 20 units=

B) Aftern preparing the quote, you fund a labor ticket for this customer for five locomotive cylinder deads. From teh notations on the labor ticket, you conclude that the fifth unit took 2.5 hours

Based on the found labor ticket, is the time quoted for the batch of 12 high or low?

The total amount of hours to build the 12 units based on the finding of the labor ticket =   

based on the found labor ticket, you would concluded that the earlier estimate is low