Question: Project 1-4: Don Funk Video:

New Task Dependencies After reviewing your project schedule, you have determined that some of the tasks could be linked in a different way to make your project more efficient.

OPEN Don Funk Music Video 1-4 from the data files for this lesson attached.

1. Change tasks 9 and 10 so that they have a start-to-start relationship.

2. Change tasks 7 and 8 so that they have a start-to-start relationship.

3. Adjust the chart area of your screen so that the Gantt bars for these new relationships are visible.

4. SAVE the project schedule as Don Funk Revised Links in the solutions folder for this lesson and then CLOSE the file.

LEAVE Project open to use in the next exercise.

Microsoft Official Academic Course. Microsoft Project 2013 (Page 35). . Kindle Edition.

  • What challenges did you find in doing this exercise? How would linking the tasks in a different way change the project? What changes did you observe in the Gantt bar?

Solution Preview :

Prepared by a verified Expert
Project Management: Save the project schedule as don funk revised links in the
Reference No:- TGS02318489

Now Priced at $20 (50% Discount)

Recommended (97%)

Rated (4.9/5)