Redraw the diagram of the network diagram


Assignment task: You are a project manager for Vintage Shades Sdn Bhd. Your company manufactures window in Penang and is taking its product to Kuala Lumpur hotel chains. It will offer its product at retail stores as well as on its website. You are developing the project schedule and looking at the following diagram:

a) Redraw the diagram of the network diagram above and calculate the Earliest Start (ES) and Earliest Finish (EF) for each activity.

b) Can the project be completed in 32 days? State your reason.

c) Which path is the critical path?

d) If the duration of activity B was changed to 10 days and the duration of activity G was changed to 9 days, which path is the critical path?