Problem on number of kanban cards


Problem: Chris Millikan Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed.

Setup cost

=

$30

Annual holding cost subassembly

=

$120 per subassembly

Daily production

=

30 subassemblies

Annual usage

=

2,500 (50 weeks × 5 days each × daily usage of 10 subassemblies)

Lead time

=

6 days

Safety stock

=

4 days' production of subassemblies.

Size of kanbans: ____________
Number of kanbans: ____________

Round your answers up to the nearest whole number; for example, round 11.2 to 12 .