Person co is considering a project that has the following


Assignment

1. K&G Co. is evaluating a project that has the following cash flow and WACC data. What is the project's discounted payback period?Show your formula and your work in details.

WACC:

5.40%

 

 

 

 

Year

0

1

2

3

4

Cash flows

-$1040

$780

$365

$450

$490

2. H&M inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Show your work in details.

WACC:

6.00%

 

 

 

 

Year

0

1

2

3

4

Cash flows

-$5000

$6000

$-5200

$-7500

$8000

3. Person Co. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that a project's expected NPV can be negative, in which case it will be rejected. You have to use the formula to address this question. No partial credit will be given if you simply use the financial calculator to answer the question.

WACC:

11.00%

 

 

 

Year

0

1

2

3

Cash flows

-$1050

$800

$200

$550

3. T&T is considering two mutually exclusive projects with the following cash flows.

 

Project A

Project B

Year

Cash Flow

Cash Flow

0

-$50,000

-$50,000

1

$31,000

$42,000

2

$26,000

$21,000

3

$27,000

$18,000

(a) What is the crossover rate? Show your work in details.

(b) If therequired rate of return is lower than the crossover rate, which project should be accepted? Why?

4.To estimate the company's WACC, B&H inc. recently hired you as a consultant. You have obtained the following information.

(1) The firm's noncallable bonds mature in 15 years, have a 7.50% annual coupon, a par value of $1,000, and a market price of $1,110.00.

(2) The company's tax rate is 34%.

(3) The risk-free rate is 2.60%, the market return is 8.50%, and the stock's beta is 1.50.

(4) The target capital structure consists of 35% debt and the balance is common equity.

The firm uses the CAPM to estimate the cost of common stock, and it does not expect to issue any new shares. What is its WACC? Show your work in details.

5.AT&T inc is evaluating a new project whose data are shown below. The project has a 4-year tax life and would be fully depreciated by the straight-line method over 4 years, but it would have a positive pre-tax salvage value at the end of Year 4, when the project would be closed down.

Also, some new working capital would be required, but it would be recovered at the end of the project's life. Unit sales and fixed costs will be constant, but the sales price and variable cost should increase with inflation. Forecast the corresponding cash flows and determine the value of this project.

WACC

10.00%

Net investment in fixed assets (depreciable basis)

$280,000

Required new working capital

$10,000

Average price per unit, Year 1

$90

Unit Sold per year

90,000 units

Variable operating cost/unit, Year 1

$32

Fixed Cost each year (not including Depreciation) (constant)

$120,000

Expected pretax salvage value

$11,000

Tax rate

35.00%

Expected inflation rate per year

2.40%

 


t = 0

t = 1

t = 2

t = 3

t = 4

Inflation

 

 

 

 

 

Price per unit

 

 

 

 

 

VC per unit

 

 

 

 

 

Units sold

 

 

 

 

 

 

 

 

 

 

 

Sales revenues

 

 

 

 

 

- Fixed op. cost (excl. deprec.)

 

 

 

 

 

- Variable op costs

 

 

 

 

 

- Depreciation

 

 

 

 

 

Operating income (EBIT)

 

 

 

 

 

- Taxes

 

 

 

 

 

After-tax EBIT

 

 

 

 

 

+ Depreciation

 

 

 

 

 

Cash flow from Operation

 

 

 

 

 

Investment in working capital

 

 

 

 

 

Capital Spending

 

 

 

 

 

Salvage value, pre-tax

 

 

 

 

 

- Tax on salvage value

 

 

 

 

 

Total cash flows

 

 

 

 

 

What is the project's NPV and IRR?  What decision should be made?

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Person co is considering a project that has the following
Reference No:- TGS02813700

Expected delivery within 24 Hours