One unit of a is made of two units of b three unit of c and


One unit of A is made of two units of B, three unit of C, and three units of D. B is composed of two units of E and one unit of D. C is made of two units of B and three units of E. E is made of two units of F. Items B, C, and E have one week lead times; A and F have lead times of two weeks; D has lead time of 3 weeks. Assume that lot-for-lot (L4L) lot sizing is used for Items A, B and F; lots of size 50, 50 and 100 are used for Items C, D and E respectively. Items C, E and F have on-hand (beginning) inventories of 20, 50 and 150 respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 2, 50 units of E in Week 1, and also 100 units of F in Week 1. There are no other scheduled receipts. a) Draw the product structure with low-level coding.