On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows:

   January 1, 2016 $313,000

  September 1, 2016 $465,000

  December 31, 2016 $465,000

  March 31, 2017 $465,000

  September 30, 2017 $313,000

 Dreamworld had $5,500,000 in 15% bonds outstanding through both years.

 Dreamworld's capitalized interest in 2016 was:

 $93,900.

$46,950.

$81,938.

$70,200.