FireKing Office Products, a manufacturer of fireproof file cabinets, uses MRP to schedule its production. Demand and inventory data for its "Signature Series Files" model are given in the table below.
 
Period         1     2     3      4      5
Demand    20    40    30    10    45

Ordering Cost = $100 per order
Holding Cost = $1 per file cabinet per week
Lead Time = 1 period
Beginning Inventory = 25

Complete an MRP matrix for the "Signature Series Files" model using:

a) No lot sizing
b) Minimum 75 lot sizing
c) Multiple 50 lot sizing

Which lot sizing rule do you recommend?