Minimize the total processing and transportation cost


Question: The cost of processing the rock is $22 per ton at Plant 1 and $18 per ton at Plant 2.

a) Formulate a linear program to minimize the total processing and transportation cost.

b) Define the decision variables.

c) What are the constraints?

d) What is the objective function?

e) What is the optimal solution?

Cost per Ton for Shipping:            
               
From Mine                               #1            #2    Daily Supply

A                                            $6             $8    320 tons
B                                            $7             $10   450 tons

Processing capacity per day      500 tons     500 tons   
               
The cost of shipping from each plant to each store and the daily demand are as follows:

Cost per Ton for Shipping               
               
From Plant     Builders'Home    Homeowners HQ    Hardware City   
#1                       $13                     $17                    $20   
#2                       $19                     $22                    $21   
Daily Demand       200                     240                    330   

Solution Preview :

Prepared by a verified Expert
Operation Research: Minimize the total processing and transportation cost
Reference No:- TGS01439140

Now Priced at $25 (50% Discount)

Recommended (98%)