Mantuach Printing is a highly automated printing company. Mantuach allocates factory overhead based on machine hours.

During a recent month, 310 machine hours were worked. These machine hours resulted in the production of 30,000 books. The production standards have an objective of 100 books per machine hour.

Facts about budgeted and actual factory overhead are as follows:

Actual total variable factory overhead for the month was $250,000.
Variable factory overhead was estimated and applied at $800 per machine hour. Actual total fixed factory overhead for the month was $120,000.
Fixed factory overhead was estimated and applied at $450 per machine hour.

Mantuach based the fixed overhead allocation rates on an assumed production level of 28,000 books.

Calculate the overhead variances.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Mantuach printing is a highly automated printing company
Reference No:- TGS02574684

Now Priced at $10 (50% Discount)

Recommended (92%)

Rated (4.4/5)