Linear programming model-satisfy the stang requirements


Discuss the below:

The manager of a computer help center needs to determine a shift schedule for his sta . The center is open from 8am until midnight (12am), and is divided into four shifts.

The number of employees needed on each shift is as follows: 4 on the rst shift (8am-12pm),10 on the second shift (12pm-4pm), 8 on the third shift (4pm-8pm), and 6 on the last shift(8pm-12am).

Two types of employees can be hired to sta the computer center: full-time employees andpart-time employees. Full-time employees must be hired for two consecutive shifts, and can behired to start in the rst, second or third shift. Part-time employees are hired for a single shift.

Full-time employees are paid $14 an hour, while part-time employees are paid $12 an hour.

Lastly, during each of the shifts, there must be at least two full-time employees stayed for everypart-time employee.

Formulate a linear programming model to satisfy the stang requirements at minimum cost.

Request for Solution File

Ask an Expert for Answer!!
Operation Research: Linear programming model-satisfy the stang requirements
Reference No:- TGS02040178

Expected delivery within 24 Hours