Joe henrys machine shop uses 120000 brackets during the


Joe Henry's machine shop uses? 120,000 brackets during the course of a year. These brackets are purchased from a supplier 990 miles away. The company operates 300 working days per year. Given an EOQ of 8,000 brackets, how many orders will be made? annually? A. 15 orders B. 150 orders C. 266 orders D. 400 orders What is the time between orders? A. 20 days B. 15 days C. 2 days D. 1.3 days.