Question: Seven Jobs must be processed in two operations:  A and B. All Seven jobs must go through A and B in that sequence – A first, then B. Determine the optimal order in which the jobs should be sequenced through the process using these times:

Job

Process A Time

Process B Time

1

9

6

2

8

5

3

7

7

4

6

3

5

1

2

6

2

6

7

4

7