Job g is a day behind schedule it started at the beginning


First Printing and Copy Center has 4 more jobs to be scheduled, in addition to those shown in Example 3 in the chapter. Production scheduling personnel are reviewing the Gantt chart at the end of day 4.

? Job D was scheduled to begin early on day 2 and to end on the middle of day 9. As of now (the review point after day 4), it is 2 days ahead of schedule.

? Job E should begin on day 1 and end on day 3. It is on time.

? Job F was to begin on day 3, but maintenance forced a delay of 1½ days. The job should now take 5 full days. It is now on schedule.

? Job G is a day behind schedule. It started at the beginning of day 2 and should require 6 days to complete. Develop a Gantt schedule chart for First Printing and Copy Center.