If klondike incurs another 2500000 of costs in the third


Question - Klondike Construction Company is building a highway under a three-year construction contract. Klondike will receive $11,200,000 for building five miles of highway. Klondike estimates that it will incur $10,000,000 of costs before the contract is completed.

At the end of year one, Klondike had incurred $3,000,000 of contract costs.

a. How much income from the contract must Klondike report for year one?

b. Assume Klondike incurs an additional $5,000,000 of costs during the second year. How much income should be reported for that year?

c. If Klondike incurs another $2,500,000 of costs in the third and final year of the contract, how much income must Klondike report for the third year?

d. Will Klondike receive or pay look-back interest?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: If klondike incurs another 2500000 of costs in the third
Reference No:- TGS02900335

Now Priced at $25 (50% Discount)

Recommended (93%)

Rated (4.5/5)