If 800 labor hours were required to produce the first unit


a) If 600 labor hours were required to produce the first unit, how many will be required for the 7th unit if an 80% learning curve is in effect?

b) If 800 labor hours were required to produce the first unit, how many will be required for the 5th unit if a 90% learning curve is in effect?