Identify the average utilization factor


Question: A set of four jobs A, B, C & D have the machining time of 5, 25, 20, and 10 hours and are due at 20, 35, 40, and 25 hours respectively. Identify the Average utilization factor (%) for CR.

Request for Solution File

Ask an Expert for Answer!!
Other Management: Identify the average utilization factor
Reference No:- TGS03212140

Expected delivery within 24 Hours