How will the number of needed containers change as the


Carlos Gonzales is production manager at an assembly plant that manufactures cordless telephones. The company is planning to install a pull system. The process is being planned to have a usage rate of 50 pieces per hour. Each container is designed to hold 10 pieces. It takes an average of 30 minutes to complete a cycle.

(a) How many containers will be needed? (b) How will the number of needed containers change as the system improves?