How reducing project duration caused by


Problem: Within the contract, it is agreed that a company will receive an extra $1,000.00 for each day the project is ahead of schedule. This is an example of reducing project duration caused by

a. Imposed project deadlines

b. time to market

c. unforeseen project delays

d. high overhead

e. incentive contracts