How much does hourly capacity of dry-cleaning machine change


Assignment

I. Show how all the Run Time and Capacity numbers in the process flow diagram in Figure 3 (page 7 of the note) were calculated. There are 6 Run Time numbers and 6 Capacity numbers. These calculations are explained in the note. Below is a table showing all details.

Processes

Run Times

Capacity Numbers

Order Taking

1 minute per item meaning 3 minutes an order

1 item per minute X 60  = 60 items an order

Pre-Treatment

60 min/56.8 items per hour = 1.06 minutes an item

90 items in 95 minutes: 

90/95 X 60 = 56.8 items

Dry Cleaning

5 minutes switching tanks and 55 minutes of run time for 90 items. 60/60 = 1 batch 

90 items an hour but can be increased if items are the same color

Pressing

24 items an hour

48 items an hour with 2 presses

Packing

0.5 minutes  per item or 2 items per minute

 120 items per hour

Customer Pick Up & Payment

1 minute per item

60 items an hour

II. What is the daily capacity (in terms of number of customers served) of the dry-cleaning process as a whole? Assume each day is 12 hours long.

III. Suppose capacity at Pressing is doubled by adding 2 persons and 2 pressing machines. What is the new daily capacity (number of customers served) of the dry-cleaning process as a whole?

IV. Customers have been complaining that stains are not removed properly. So the laundry reduces the batch size in pre-treatment to 75 items. Pre-treatment still takes 90 minutes plus 5 minutes for solvent tank change. Now what is the hourly capacity of pre-treatment? How does this impact the overall capacity of the process?

V. How much does the hourly capacity of the dry-cleaning machine change if the batch size is increased to 120 items from 90 items?

VI. How much does the hourly capacity of the dry-cleaning machine change if tanks are switched only every 5 runs?

VII. Suppose 200 customers drop off laundry over a typical 12-hour day. What is the utilization of each of the different stages of the dry-cleaning process? Show in the form of a table. Will there be a problem? Do not consider the changes suggested in questions 3-6.

VIII. If the average number of clothes per customer increases from 3 to 4, which stages would be most impacted by this? Assume 180 customers per 12-hr day as stated in the case. Answer by calculating the utilization at each stage. Is the current system capable of dealing with this increase?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: How much does hourly capacity of dry-cleaning machine change
Reference No:- TGS03227478

Expected delivery within 24 Hours