How many labor hours should johnson estimate are needed for


Johnson Industries received a contract to develop and produce four high-intensity long-distance receiver/transmitters for cellular telephones.

The first took 2, 200 labor hours and $40,000 worth of purchased and manufactured parts; the second took 1, 340 labor hours and $28, 400 in parts; the third took 1, 070 labor hours and $24,000 in parts; and the fourth took 791 labor hours and $19, 600 in parts. Johnson was asked to bid on a follow-on contract for another dozen receiver/transmitter units.

a. How many labor hours should Johnson estimate are needed for the additional 12 units?

b. How much should Johnson estimate the parts cost will be for the additional 12 units?