How long does the project take to completenbspwe ask the


Consider a project consisting of four activities A, B, C, and D.

a) A and B, the first activities of the project, can be started simultaneously.

b) C can be started only after A is completed.

c) D can be started only after B is completed

Suppose the activity times for the activities are A = 2 weeks, B = 2 weeks, C = 2 weeks, D = 2 weeks.

a) How long does the project take to complete?

b) We ask the engineer working on activity A to factor in uncertainty in activity times and to provide better estimates of the activity times. The engineers tell us that activity A takes 1 week 50% of the time, and 3 weeks 50% of the time. How long does the project now take to complete (on average)?

c) We now also ask the engineer working on activity B to factor in uncertainty in activity times and to provide better estimates of the activity times. The engineer now tell us that activity B takes 1 week 50% of the time, and 3 weeks 50% of the time. How long does the project now take to complete (on average)? [ASSUME THAT BOTH ACTIVITY A AND ACTIVITY B ARE UNCERTAIN]

Request for Solution File

Ask an Expert for Answer!!
Operation Management: How long does the project take to completenbspwe ask the
Reference No:- TGS01511804

Expected delivery within 24 Hours