How long does it take the agency to issue the permit


Problem 1: A government agency is responsible for approving all the construction permits for all the state healthcare related facilities. Annually, the agency receives about 350 permits. The permits await assignment to an agent who has to approve the project once all the requirements are satisfied. A year is considered 250 calendar days. The process map is shown. On average how many permits are submitted per day?

A. 1.4 permits

B. 1 permit

C. 350 permits

D. 250 permits

Problem 2: A government agency is responsible for approving all the construction permits for all the state healthcare related facilities. Annually, the agency receives about 350 permits. The permits await assignment to an agent who has to approve the project once all the requirements are satisfied. A year is considered 250 calendar days. The process map is shown. On average how many permits are awaiting assignment?

A. 350 permits

B. 14 permits

C. 61.6 permits

D. 75.6 permits

Problem 3: A government agency is responsible for approving all the construction permits for all the state healthcare related facilities. Annually, the agency receives about 350 permits. The permits await assignment to an agent who has to approve the project once all the requirements are satisfied. A year is considered 250 calendar days. The process map is shown ). On average how many permits are in the approval process?

A. 350 permits

B. 14 permits

C. 61.6 permits

D. 75.6 permits

Problem 4: A government agency is responsible for approving all the construction permits for all the state healthcare related facilities. Annually, the agency receives about 350 permits. The permits await assignment to an agent who has to approve the project once all the requirements are satisfied. A year is considered 250 calendar days. The process map is shown. On average how long does it take the agency to issue the permit (total time)?

A. 10 days

B. 44 days

C. 54 days

D. 250 days

Problem 5: A government agency is responsible for approving all the construction permits for all the state healthcare related facilities. Annually, the agency receives about 350 permits. The permits await assignment to an agent who has to approve the project once all the requirements are satisfied. A year is considered 250 calendar days. The process map is shown. On average how many permits are with the agency (awaiting assignment and approval process)?

a. 350 permits

b. 14 permits

c. 61.6 permits

d. 75.6 permits

The main reason behind the popularity of our Income Tax Accounting Assignment Help service is our in-house professional tutors, who work day and night and put their maximum effort in order to make your assignment paper of the top quality.

Tags: Income Tax Accounting Assignment Help, Income Tax Accounting Homework Help, Income Tax Accounting Coursework, Income Tax Accounting Solved Assignments

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: How long does it take the agency to issue the permit
Reference No:- TGS03041322

Expected delivery within 24 Hours