Hospitality enterprises is planning to build a new 112 room


Hospitality Enterprises is planning to build a new 112 room inn in Martin. The initial cost of land leases and construction is anticipated to be $3.4 million. The annual operating and maintenance costs are expected to average $25,000 for the 20-year life of the inn. Every 4 years the interior of the inn must be painted at a cost of $15,000. The exterior must be painted and refurbished every 5 years at a cost of $60,000. The carpet and furniture must be replaced every 6 years at a cost of $100,000. Every 8 years $80,000 will be spent on paving and striping the parking areas. The inn will have a net demolition cost of $100,000 at the end of its life. If the MARK for Hospitality is 5%, determine the EUAC for the inn. Contributed by Ed Wheeler, University of Tennessee at Martin.