Given the information from this integrated program


Given the information from this Integrated Program Management Report (IPMR) Form might you expect to find in Format 5 of the IPMR?

(IMAGE DESCRIPTION: IPMR Format 3 contract data values, in thousands of dollars, are negotiated cost $64,711.5; b. negotiated contract changes $65.4; c. current negotiated c $64,776.9; d. estimated cost of authorized unpriced work $2,129.0; e. contract budget ba $66,905.9.)

a. Detailed staffing forecast

b. The contractor’s internal detailed log of all changes made to the PMB

c. Detailed Integrated Master Schedule tasks and planning packages

d. An explanation of the authorized unpriced work (AUW)