Given is a cpm project network diagram as shown


Given is a CPM project network diagram as shown below.

1140_Untitled.png

The Project Completion time = ______________ days.

The Earliest Start time, ES, of Activity G = ______________ days.

The Latest Finish time, LF, of Activity C = _____________ days.

The critical activities are = _________________ (ex. Fill in answer as: ABCD)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Given is a cpm project network diagram as shown
Reference No:- TGS02163350

Expected delivery within 24 Hours