First-stage allocation of overhead costs


Problem: Imai Draperies makes custom draperies for homes and businesses. The company uses an activity-based costing system for its overhead costs. The company has provided the following data concerning its annual overhead costs and its activity cost pools.

Overhead costs:

Production overhead . . . .  $240,000
Office expense . . . . . . . . .  160,000
Total . . . . . . . . . . . . . . . . .400,000

Distribution of resource consumption:

Making Job
Activity Cost Pools Drapes Support Other Total

Production overhead 35% 45% 20% 100%
Office expense         15%  55% 30% 100%

The "Other" acticity cost pool consists of the costs of idle capacity and organization-sustaining costs.

The amount of activity for the year is as follows:

Activity Cost Pool Annual Activity
Making drapes . . . . . 4,000 yards
Job support . . . . . . . 100 jobs
Other . . . . . . . . . . . . Not applicable

Required:

Q1. Prepare the first-stage allocation of overhead costs to the activity cost pools by filling in the table below:

Making Job
Drapes Support Other Total
Production overhead . . .
Office expense . . . . . . .
Total . . . . . . . . . . . . . . .

Q2. Compute the activity rates (i.e., cost per unit of activity) for the Making Drapes and Job Support activity cost pools by filling in the table below:

Making Job
Drapes Support
Production overhead . . .
Office expense . . . . . . . .
Total . . . . . . . . . . . . . . .

Solution Preview :

Prepared by a verified Expert
Accounting Basics: First-stage allocation of overhead costs
Reference No:- TGS01620870

Now Priced at $25 (50% Discount)

Recommended (98%)

Rated (4.3/5)