Find the critical pathwhat is the project completion


ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (days)

A 9

B A 7

C A 3

D B 6

E B 9

F C 4

G E,F 6

H D 5

I G,I 3

a) Draw the PERT diagram (aka AON diagram) for the Merritt Construction team.

b) Find the critical path.

c) What is the project completion time?